
上QQ阅读APP看本书,新人免费读10天
设备和账号都新为新人
4.11 Steam—Water Centralized Sampling,Feedwater,Boiler water Treatment System
4.11.1 Installation of sampling rack.
1 Scope of application:steam-water sampling device.
2 Inspection quantity:check them item by item.
3 Quality standards and inspection methods are as shown in Table 4.11.1.
Table 4.11.1 Installation of sampling rack

4.11.2 Inspection of the compulsory provision implementation of the steam-water centralized sampling,feedwater,boiler water treatment system shall conform to Table 4.11.2.
Table 4.11.2 Inspection table of compulsory provision implementation of the steam—water centralized sampling,feedwater,boiler water treatment system

Table 4.11.2(Continued)
